Loser Panoramabahn: Precision and Professionalism in Action

ALPINE ROPEWAYS

The towers were successfully installed at the Loser project, marking a significant milestone toward completion. Out of the total 21 towers, 10 are situated in difficult-to-access terrain, requiring a helicopter for the installation.
 

The pilot and crew worked for several hours, completing numerous flights to transport loads of up to 4,000 kg to the site. New towers were installed while simultaneously dismantling the old system's towers. The remaining towers will now be installed using a crane.